Campus Development

At UNIS Hanoi we know that learning spaces and facilities are integral to providing the best possible learning experience for our students.

We are committed to a master plan to not only create new learning spaces but to also renovate and renew existing spaces.

In June 2016 we started Phase 3A of our Master Plan to be completed by August 2018 and which includes:

  • A new cafeteria and testing centre with student and faculty lounges and a community garden
  • A new wing to the Elementary School
  • An extended and fully renovated covered court area
  • An artificial turf soccer pitch for all year use.

Discover more about the Master Plan and its Phases 3A-D below.

Due to the plan's size and projected costs it is divided into five separate phases, each to be approved, financed and constructed separately according to the financial indicators at the time and to ensure prudent financial planning.

The Master Plan

Phase 3A

PHASE 3A: Approved by the Board of Directors
DURATION: June 2016 - August 2018

 

NOTES (New construction in bold):

1a. Contractor Site Office location and Main Access Gate for construction works

1. Temporary Access Gate during construction

2. Construction of a Temporary Perimeter Fence

3. Dismantling of the roof at the Covered Court

4. Piling, foundation and underground utility construction

5. NEW COVERED OUTDOOR COURTS

6. NEW DINING / TESTING CENTRE

7. NEW ELEMENTARY WING

8. NEW FOOTBALL FIELD WITH ARTIFICIAL GRASS

9. NEW CENTRAL PLANT STRUCTURE

10. Storing of excavated soil at the side of the large sport field (to be used later on as backfilling materials).

Phase 3B

 
PHASE 3B: To be approved by the Board of Directors
 

NOTES (New construction in bold):

1a. Contractor temporary office location and access gates

1. Temporary access gates

2. Construction area perimeter fence

3. Libarary dismantling and demolition works

4. Piling, foundation and underground utilities

5. ECC RENOVATION

6. FOOTBALL FIELD WITH NATURAL GRASS + RUNNING TRACK + BLEACHERS

7. PARKING AREA 1

8. WELCOME CENTRE CONSTRUCTION

9. ECC MOTOR SKILLS CONSTRUCTION

10. BLACK BOX CONSTRUCTION

11. MAIN ENTRANCE GATE

12. NEW BICYCLE GATE

13. SPORTS FACILITY STORAGE

14. LIBRARY / TECHNOLOGY / WORLD LANGUAGE CENTRE

15. Black Box soft landscape

Phase 3C

PHASE 3C: To be approved by the Board of Directors
 
NOTES (New construction in bold):
 

1. Gates for construction access

2. Constuction area perimeter fence

3. Dismantling and demolition works

4. Piling, foundation and underground utilities

5. ELEMENTARY BUILDING RENOVATION;

6. ADMINISTRATION BUILDING RENOVATION;

7. MIDDLE SCHOOL AND HIGH SCHOOL BUILDING RENOVATION;

8. ECC RENOVATION

Phase 3D

PHASE D1: To be approved by the Board of Directors
 
NOTES (New construction in bold)D1
 

1. Temporary access gate for construction

2. Construction area perimeter fence

3. UN PLAZA

4. Piling, foundation and underground utilities

5. PARKING AREA 2

6. SEMI COVERED ROOF FOUNDATION FOR FOOTHPATH;

7. FOOTHPATH / WALK WAY

8. Remaining soft and hard landscape works.

9. SMALL EXTERNAL RENOVATION WORKS;

10. Demolition works for swimming pool and sports centre building.

PHASE D2: To be approved by the Board of Directors
 

NOTES(New construction in bold)D2

  1. ADDITIONAL COVERED GYMNASIUM AND CLIMBING WALL

  2. 50m SWIMMING POOL

 

Project Partners

UNIS Hanoi partners with the following teams for its campus development:

Mace Vietnam Company Limited, Project and Construction Management, David Watkins - General Director

Group GSA (Vietnam), Lead Design Consultant, Matthew Young - General Director

BHA Studio Limited, Architectural Design Consultant, Barnaby Hewitt - Managing Director

Boydens+NEY Engineering, Engineering Design Consultant, Xavier Pinchart - General Director

NDC Consulting, 3rd Party and Authority Submission Consultant, Le Thi Bich Lien - President, CEO

WT Partnership (Vietnam) LLC, Cost Consultant, David McDonald - General Director 